Status of Chandra Mission

Activity & Schedule Completion Status
[ 0% - 100% ]
separator line
Scientific Operations
Ongoing
bar
On orbit Calibration
August 7, 1999 - September 1999
bar
Launch!!
July 23, 1999
bar
Chandra/IUS transfer to Columbia
June 1999
bar
Launch Preparation at KSC
February 1999 - July 17, 1999
bar
Chandra arrive at KSC
February 4, 1999
bar
Observatory Assembly & Testing
October 1997 - June 1999
bar
Telescope Assembly & Testing
April 1997 - September 1997
bar
Spacecraft Assembly & Testing
April 1997 - October 1997
bar
Mirror & Instrument Calibration
November 1996 - April 1997
bar
Spacecraft Structure Fabrication
December 1995 - March 1997
bar
Integral Propulsion System
December 1993 - March 1997
bar
Science Instrument Development
January 1990 - January 1997
bar
Mirror Assembly
July 1995 - November 1996
bar
Mirror Grinding & Polishing
December 1991 - July 1995