Operations CXO Status Report

Friday 4 August 2006 8.00am EDT

During the last week Chandra completed the observing schedule as planned.

A real-time procedure was conducted on July 31 to uplink a flight software patch to OBC-B to add on-board monitoring of selected propulsion line and valve temperatures. This completes the procedure conducted on July 27 during which the patch was uplinked to OBC-A.

The schedule of targets for next week is shown below and includes an observation of 4U 1820-30 coordinated with RXTE and the VLA.

------------------------------------------
HZ43                    HRC-S/LETG   Aug 7
IRAS05436-0007          ACIS-I
A3074                   ACIS-I
Radiation Belts                      Aug 8
GS 1826-238             ACIS-S/HETG
Radiation Belts                      Aug 11
GS 1826-238             ACIS-S/HETG
Q1431+3952              ACIS-S       Aug 12
SDSS J160207.6+380      ACIS-S
M81*                    ACIS-S/HETG
1RXS J155705.0+383      ACIS-S
4U 1820-30              ACIS-S/HETG
A3074                   ACIS-I       Aug 13

------------------------------------------

All spacecraft subsystems continued to support nominal operations.