Operations CXO Status Report

Friday 27 January 2023 9.00am EST

During the last week Chandra completed the observing schedule as planned.

Of note this week was the announcement on Jan 25 that the Chandra science and engineering teams are preparing to return the HRC to use for science observations. Current plans are to begin scheduling HRC observations in the regular spacecraft loads beginning with the week of 06 March 2023, although some testing of the schedule generation is still underway.

The schedule of targets for the next week is shown below and includes an observation of AT2022tsd, which is a follow-up to a Target of Opportunity accepted on Oct 7, and is coordinated with NuStar and an observation of DGPS J160716.9-52081, which is a follow-up to a Target of Opportunity accepted on Oct 6.



------------------------------------------
        Radiation Belts                     Jan 30
        AT2022tsd              ACIS-S
        DELSJ091054.53-0414    ACIS-I       Jan 31
        DGPSJ160716.9-52081    ACIS-I
        PSRJ1136-5525          ACIS-I
        DELSJ091054.53-0414    ACIS-I
        SDSSJ1339+1310         ACIS-S
        SN2016jae              ACIS-S       Feb  1
        V750Ara                ACIS-S/HETG
        SN2016jae              ACIS-S
        Radiation Belts                     Feb  2
        SDSSJ152156.48+5202    ACIS-S
        MKN421                 ACIS-S/LETG
        HS1549Protocluster     ACIS-S       Feb  3
        CFHQSJ142952+544717    ACIS-S
        SN2016jae              ACIS-S
        V750Ara                ACIS-S/HETG
        SN2016jae              ACIS-S       Feb  4
        SNRG310.6-1.6          ACIS-S
        DELSJ091054.53-0414    ACIS-I
        Radiation Belts
        HS1549Protocluster     ACIS-S
        SDSSJ092216.04+1605    ACIS-S       Feb  5
        HS1549Protocluster     ACIS-S
        DELSJ091054.53-0414    ACIS-I
        SNRG310.6-1.6          ACIS-S
        DELSJ091054.53-0414    ACIS-I

------------------------------------------

All spacecraft subsystems except HRC continued to support nominal operations.